What Is a Master Production Schedule (MPS), and How Do You Create One?

A Master Production Schedule shows which principal products to make, in what period and in what quantity. It helps you prepare a workable production plan by considering orders, demand forecasts, usable inventory and production capacity together.

What decisions does an MPS support?

MPS creates a master, period-based plan between demand and production. It makes visible which products and quantities are needed for orders, how inventory targets will be maintained and what load production resources will face.

What will be produced?

Identifies the finished goods or principal product groups in scope.

When will it be produced?

Places production quantities into weekly or monthly periods.

How much will be produced?

Considers demand alongside usable inventory and confirmed receipts.

What information do you need before planning?

Orders and demand

Confirmed customer orders, due dates and period forecasts, where used.

Usable inventory

Opening inventory, reservations, quality blocks and the safety-stock policy.

Scheduled receipts

Production orders and purchase deliveries expected on time.

Product and production data

Product groups, production lead times, work centers, shifts and critical capacity constraints.

How do you create an MPS in 7 steps?

  1. 1

    Set the planning horizon and time buckets

    Build the plan in weekly or monthly periods. Choose a cadence that fits order frequency, production lead times and the business review cycle. Using the same periods across products makes comparisons easier.

  2. 2

    Combine order and demand information

    Place confirmed customer orders and, where used, demand forecasts into periods. Define how forecasts are consumed so the same demand is not counted once as a forecast and again as a confirmed order.

  3. 3

    Check usable inventory and scheduled receipts

    Separate opening usable inventory, allocated quantities and production or purchase receipts expected on time. Do not treat quality-blocked or already reserved stock as freely available.

  4. 4

    Select products and set priorities

    Choose the finished goods or principal items in scope. Make the prioritisation criteria explicit, such as due dates, customer priority, product family, inventory policy and critical production resources.

  5. 5

    Calculate production quantities by period

    When determining the quantity needed to cover demand and the target ending inventory, account for opening usable stock and confirmed receipts. Keep the calculation visible for each product and period.

  6. 6

    Validate capacity and material availability

    Compare draft quantities with work-center loads, shifts, routing times and critical materials. The MPS sets the plan for principal items; detailed component requirements are calculated in the subsequent MRP run. If capacity or material is constrained, review alternative dates and quantities before approval.

  7. 7

    Approve the plan and review actual results

    Define who prepares, reviews and approves the plan. Clarify who may change near-term quantities. Each period, compare actual orders, production, inventory and capacity with the plan and record the reasons for variances.

A simple MPS quantity example

This is a simplified planning example for one product in one period. In a live plan, business-specific rules such as reservations, scrap, lot sizes, due dates and capacity also need to be considered.

Period demand

90 units

Target ending inventory

10 units

Opening usable inventory

25 units

Confirmed production receipt

15 units

Simplified planned production quantity: 90 + 10 − 25 − 15 = 60 units

In this example, a 60-unit production plan covers period demand and the target inventory. It assumes demand contains no order/forecast overlap and that the listed receipts will be available on time.

MPS, MRP and capacity planning are different

MPS

Plans which principal products to make, in what period and quantity.

MRP

Uses bills of materials and inventory data to calculate component requirements.

Capacity planning

Checks whether production quantities are feasible against work centers, shifts and available time.

Frequently asked questions about MPS

What is a Master Production Schedule (MPS)?

A Master Production Schedule shows the planned quantity and period for selected finished or principal items. It brings demand, inventory, production receipts and capacity review into one plan.

What is the difference between MPS and MRP?

MPS plans period quantities for principal items. MRP uses that plan and data such as bills of materials to calculate when and how much of lower-level components is required.

How often should an MPS be updated?

One update cadence does not suit every business. Set a regular review interval based on order changes, supply lead times, production cycles and the planning team’s review calendar; also define how urgent changes are approved.

Does MPS account for capacity?

Yes. Draft quantities should be checked against available production resources. MPS is not, by itself, a detailed capacity schedule; work-center loads, shifts and operation times need separate validation.

Build the MPS around the business’s product structure, demand patterns, inventory policy and production constraints. Review the plan as data changes and define update ownership in advance.

Did You Find This Page Useful?

Related content

Continue with guides, products and resources related to this topic.

Your privacy is important to us

We use cookies to improve your experience while visiting our site, provide our services, and fulfill our legal obligations. Click for more information.