What will be produced?
Identifies the finished goods or principal product groups in scope.
Production planning guide
A Master Production Schedule shows which principal products to make, in what period and in what quantity. It helps you prepare a workable production plan by considering orders, demand forecasts, usable inventory and production capacity together.
MPS creates a master, period-based plan between demand and production. It makes visible which products and quantities are needed for orders, how inventory targets will be maintained and what load production resources will face.
Identifies the finished goods or principal product groups in scope.
Places production quantities into weekly or monthly periods.
Considers demand alongside usable inventory and confirmed receipts.
Confirmed customer orders, due dates and period forecasts, where used.
Opening inventory, reservations, quality blocks and the safety-stock policy.
Production orders and purchase deliveries expected on time.
Product groups, production lead times, work centers, shifts and critical capacity constraints.
Build the plan in weekly or monthly periods. Choose a cadence that fits order frequency, production lead times and the business review cycle. Using the same periods across products makes comparisons easier.
Place confirmed customer orders and, where used, demand forecasts into periods. Define how forecasts are consumed so the same demand is not counted once as a forecast and again as a confirmed order.
Separate opening usable inventory, allocated quantities and production or purchase receipts expected on time. Do not treat quality-blocked or already reserved stock as freely available.
Choose the finished goods or principal items in scope. Make the prioritisation criteria explicit, such as due dates, customer priority, product family, inventory policy and critical production resources.
When determining the quantity needed to cover demand and the target ending inventory, account for opening usable stock and confirmed receipts. Keep the calculation visible for each product and period.
Compare draft quantities with work-center loads, shifts, routing times and critical materials. The MPS sets the plan for principal items; detailed component requirements are calculated in the subsequent MRP run. If capacity or material is constrained, review alternative dates and quantities before approval.
Define who prepares, reviews and approves the plan. Clarify who may change near-term quantities. Each period, compare actual orders, production, inventory and capacity with the plan and record the reasons for variances.
This is a simplified planning example for one product in one period. In a live plan, business-specific rules such as reservations, scrap, lot sizes, due dates and capacity also need to be considered.
Period demand
90 units
Target ending inventory
10 units
Opening usable inventory
25 units
Confirmed production receipt
15 units
Simplified planned production quantity: 90 + 10 − 25 − 15 = 60 units
In this example, a 60-unit production plan covers period demand and the target inventory. It assumes demand contains no order/forecast overlap and that the listed receipts will be available on time.
Plans which principal products to make, in what period and quantity.
Uses bills of materials and inventory data to calculate component requirements.
Checks whether production quantities are feasible against work centers, shifts and available time.
A Master Production Schedule shows the planned quantity and period for selected finished or principal items. It brings demand, inventory, production receipts and capacity review into one plan.
MPS plans period quantities for principal items. MRP uses that plan and data such as bills of materials to calculate when and how much of lower-level components is required.
One update cadence does not suit every business. Set a regular review interval based on order changes, supply lead times, production cycles and the planning team’s review calendar; also define how urgent changes are approved.
Yes. Draft quantities should be checked against available production resources. MPS is not, by itself, a detailed capacity schedule; work-center loads, shifts and operation times need separate validation.
Build the MPS around the business’s product structure, demand patterns, inventory policy and production constraints. Review the plan as data changes and define update ownership in advance.
Continue with guides, products and resources related to this topic.
Prepare a workable production plan by comparing available work center capacity with production workload.
ERP GuidesPrepare a budget view by bringing together pre-production cost assumptions by model, order and period.
ERP GuidesPlan pre-production readiness by consolidating model requirements from different orders by period and material.