Available capacity
Scheduled working time − breaks, maintenance and other planned downtime. Keep calendars and shifts by resource.
Production planning guide
Production capacity planning compares the work that can be performed by work centers during a period with the workload required by production orders. Considering calendars, shifts, routes and operation times together helps identify overloads and gaps earlier.
Scheduled working time − breaks, maintenance and other planned downtime. Keep calendars and shifts by resource.
Route operation times for the production quantity + setup times. Specify the quantity or batch to which the times apply.
Example: a work center has 40 net available hours per week and a planned workload of 46 hours. After validating time and calendar data, the 6-hour overload can be assessed through sequencing, alternative resources or period and shift options. This simple example does not account for efficiency or product-mix effects.
Choose whether the plan covers daily, weekly or monthly periods. Define the products, production area and work centers in scope; a long-term master plan and a short-term shop schedule need different levels of detail.
Check shifts, working days, holidays and planned maintenance for each work center. Apply a consistent rule for deducting breaks and maintenance when determining net available time.
Match planned quantities with the operations in product routes. Use the quantity or batch basis for setup and processing times to calculate each work center’s load by period.
Compare available time with estimated workload for each resource and period. Where load exceeds capacity, review the overload; where capacity is unused, consider whether work can be balanced into that period.
Consider resequencing work, using a suitable alternative machine, adjusting shifts or overtime, moving work to another period or using subcontracting capacity. Evaluate due dates, cost and material availability with the relevant teams.
As production progresses, compare actual operation times and stoppages with the plan. If deviations occur, review route times, calendars, quantities or recorded production data and update the next plan.
A basic approach is to subtract unavailable time, such as breaks and planned downtime, from a resource’s working calendar for the planning period. Workload is calculated from production quantity, routes, operation times and setup times. Time units and efficiency assumptions should be explicit.
Capacity planning checks whether requested workload fits available resource capacity across periods. Scheduling places jobs into a more detailed sequence on resources and time slots. In practice, the two activities inform each other.
The ratio of workload to available capacity helps show loading by resource and period. The percentage alone is not enough; maintenance, product mix, variable cycle times, bottlenecks and due-date priorities also matter.
First check the accuracy of time, calendar and route data. Then assess sequencing, alternative resources, shift or overtime options, moving work between periods or subcontracting. Consider each option alongside due dates, cost and material availability.
Capacity plans rely on estimates and should be updated with actual times and downtime once production begins. Start with accurate calendars and routes, then monitor workload and capacity deviations regularly.
Continue with guides, products and resources related to this topic.
Calculate production capacity by machine, shift, cycle time, planned downtime, performance and quality rate; Identify the bottleneck by example.